Use Cases
SPAR Store (24): 570 m² of flooring replaced in 3 days over severely damaged tile
- Client: SPAR
- Industry: Food Retail
- Area: 570 m²
- Location: Dordogne (24)
- Completion date: November 2023
- Timeframe: 3 days, 3 installers
- Service: Supply and installation of MOSAIK-FLOOR
- Existing surface: Severely damaged tile flooring
Constraints
- Heavily damaged tile
- Very short installation time
Solution
- Tiles from the DESIGN line, gray finish
- Glue-free installation over existing tile
- 3 MOSAIK-FLOOR installers, 3 days
In brief: In the Dordogne (24), the SPAR store renovated 570 m² of retail space in November 2023 using tiles from the DESIGN line. Three MOSAIK-FLOOR installers laid them without adhesive in three days, directly over heavily damaged tile flooring, to meet a very tight deadline.
Photos from the construction site
This Project by the Numbers
- 570 m² of tiles from the DESIGN line
- 3 days of installation, 3 MOSAIK-FLOOR installers
- No adhesive, no need to remove the old tiles
Frequently Asked Questions About This Construction Project
Can you install new flooring in a store over damaged tile?
Yes: At the SPAR in Dordogne, the DESIGN series tiles were installed without adhesive directly over severely damaged tile flooring, without removing the old flooring.
How long does it take to replace the flooring in a 570 m² store?
On this job site, three days with a team of three MOSAIK-FLOOR installers.
Should the tiles be glued down?
No: On this job site, the slabs were installed without adhesive, which speeds up the installation process.
Why choose pavers instead of new tile?
The tiles are installed directly over the existing floor, without the need to remove the old flooring or allow for drying time: this is what made it possible to meet the store's very tight deadline.
Do you have a similar project?
Updated on November 14, 2026.